1)Which one of the following statements is not correct for heading and benching method of tunneling ?
 A. Drilling and mucking can be done simultaneously
 B. Benching provides a platform for working on heading
 C. Removal of muck from the heading is very easy 
 D. None of these.

2)The difference of heights of the tunnels above rail tops of BG and MG tracks is kept 
A. 0.30 m
B. 0.45 m 
C. 0.60 m
D. 0.75 m

3) In case of drift method of tunneling, the drift may be excavated at
 A. the centre
 B. the bottom
 C. the top
 D. the side
 E. All of the above

 4) A tunnel is found more advantageous as compared to the alternate routes because it:
 A. remains free from snow
 B. reduces the cost by reducing the route distance
 C. reduces the maintenance cost 
 D. avoids interference with surface rights 
 E. All the above. 

5) For B.G. single track railway, the height of the tunnel above top of rails should be
A. 5.5 m to 5.8 m 
B. 5.8 m to 6.2 m 
C. 6.7 m to 7.3 m 
D. 7.3 m to 7.5 m 

6) Pick up the correct statement regarding drilling a tunnel from the following:
A. Holes are drilled by pneumatically operated rock drills 
B. One drill is required for each 4 to 5m2 force area 
C. The diameter of the bore hole at the deepest point should be 6 mm more than the diameter of the cartridge
D. All of the above.

7)For tunnels exceeding 300 m in length, the grade should be provided below
A. 50% of the ruling gradient 
B. 60% of the ruling gradient 
C. 75% of the ruling gradient 
D. 80% of the ruling gradient.

8)The method of draining in the tunnels, is generally known as
A. fore drainage 
B. dewatering 
C. permanent drainage 
D. All of the above.

9) Pick up the correct statement from the following during tunnel excavation,
A. Oxygen should not be less than 19.5%
B. Carbon dioxide should not be more than 0.5% 
C. Hydrogen sulphide should not be more than 0.001% 
D. Carbon mono-oxide should not be more than 0.01% 
E. All of the above

10)To attain the required shape of the tunnel section, we use
A. easiers
B. trimmers 
C. cut holes 
D. chisels.

11)The most commonly adopted pattern of cut holes is
A. horizontal wedge cut 
B. pyramid cut 
C. fan cut 
D. V-cut 
E. All the above

12)Which one of the following linings is suitable for shield driven tunnels particularly in the subaqueous regions
A. Brick lining 
B. stone lining 
C. timber line 
D. cast iron lining 
E. concrete lining. 

13)In case of railways
A. a detour round the hill is preferred 
B. a open cut is preferred 
C. tunnelling is preferred 
D. All the above.

14)The following tunnels were constructed in different countries for different purposes : 
1. Emperor Claudius built the first Roman tunnel 
2. The first highway tunnel was constructed in Hungary 
3. The first underground railway tunnel was constructed in Great Britain 
4. The first navigational tunnel was constructed in France.
 The correct chronological development of these tunnels is:
A. 4 1 3 2 
B. 1 4 2 3 
C. 2 3 1 4
D. 3 2 4 1 

15)The following operations are generally employed for tunnelling in hard rock. 
1. Removing ground water, 
2. Loading holes and firing the explosive 
3. Setting up and drilling 
4. Grouting and lining 
5. Removing muck 
6. Ventilation and removing explosion dust 
The correct sequence is :
A. 3 2 6 5 1 4 
B. 3 4 6 1 5 2 
C. 4 1 2 3 6 5 
D. 5 4 2 1 3 6

16)Pick up the mechanical ventilation method used for tunnels from the following
A. blowing fresh air by ducts to the face of tunnel 
B. exhausting foul air by ducts from the face of the tunnel and permitting fresh air through the tunnel
C. blowing fresh air and exhausting foul air by ducts 
D. all the above

17)Which one of the following methods of tunnelling does not require the use of time bearing
A. Linear plate method 
B. Shield method 
C. Compressed air method 
D. Mechanical tunneler i.e. mole method 
E. All the these.

18)For highways, tunnelling is preferred to if the open cut exceeds
A. 10 metres depth
B. 15 metres depth 
C. 20 metres depth 
D. 25 metres depth.

19) The following operations are required for tunnelling in rocky terrain : 
1. Removing the foul gases 
2. Marking the tunnel profile 
3. Setting up and drilling 
4. Checking misfire 
5. Mucking 
The correct sequence is 
A. 1 2 3 4 5 
B. 2 3 5 4 1 
C. 4 2 1 3 5 
D. 2 3 1 4 5 

The advantages of providing a pair of tunnels as compared to only one large highway tunnel is :
A. economy in cost of construction 
B. avoidance of head on collisions 
C. provision of separate exit and entrance of two traffic streams 
D. facility in carrying out repairs 
E. All the above.




Comments

Popular posts from this blog

METHOD OF TUNNELING IN SOFT ROCK

A Key article to learn " Method of Tunneling in Soft Rock " providing easy access to learn     Classification of  Method of tunneling in soft rock  1)Hard rock or fully self supporting 2)Soft soils  requiring temporary support during and after construction. Forepoling Method      Sequence of operation The shaft is sunk from surface to the grade level and properly protected with timber sheeting A wooden bent properly braced is setup a few inches from sheeting Small holes at close interval are drilled through the sheeting to facilitate section being cutout.The pattern of holes are 3 inches apart above the cap and other lines of holes below the cap A peice of sheeting is cutout along the top lines of the holes Forepoles or spiles consists of planks with wedge end are entered one at a time and driven through cut,into the ground for half their lengths with an upward inclination of 2 inch per foot. After all the roof and part of side spiles are driven to half their length a timber

Previously Asked Question

Here you will get to know on which way we are going and how we will reach the destination 1. Pick up the explosive used for tunneling in soft rocks from the following :  A. Special gelatine B. Blasting gelatine C. Ammonia dynamite D. Semi-gelatine 2. Which one of the following tunnelling method is used for lying underground sewers ? A. Needle beam method B. German method  C. Army method D. English method 3. To attain the required shape of tunnel we use : A. Cutholes B. Chisels C. Erasers D. Trimmers 4. For initial surveys of tunnel, the following activities are involved :  a. Marking portal points with concrete pillars on the ground.  b. Marking tunnel obligatory points on the topograpical maps. c. Driving lines between the fixed obligatory points. d. Preliminary setting of the tunnel on the topograpical survey of Indian maps. The correct sequence of the activities are :  A. b,a,d,c B. a,b,c,d C. d,b,c,a D. c,b,d,a 5. If 'D' is a diameter of the tunnel in meters, then the thick

How to Reduce Carbon dioxide from cement?

Get an overview to learn the Basics of properties of cement and know how the carbon dioxide is being removed                          ABSTRACT Concrete is the most widely used building material in the world because of its beauty, strength, and  durability, among other benefits. Concrete is used in nearly every type of construction, including  homes, buildings, roads, bridges, airports, and subways. And in an era of increased attention to the  environmental impact of construction, concrete performs well when compared to other building  materials. As with any building product, the production of concrete and its ingredients does require energy  that in turn results in the generation of carbon dioxide, or CO2. The amount of CO2 produced during  manufacturing and the net impact of using concrete as a building material is relatively small. The  following features of concrete construction help minimize its carbon footprint. Atmospheric concentrations of CO2 are expressed in units of parts per