Skip to main content

Drilling in Tunnel

DRILLING IN TUNNEL




Basics Definations:

  1. Percussion Drill:Machine which break rock into small peices by the impact of repeated blows 
  2. Abrasion Drill: In this bit rotate in hole
  3. Jack Hammer/Sinkers:Itis an air operated percussion drill type(reciprocate @ 2200 blows per minute) Weight - 20 to 25 kg
  4. Drifter – Similar to jack hammer but make hole bigger in size about 11.25cm in dia Wagon drill: Mounted on mast supported by two or more wheels
  5. Stopper:It is air operated percussion type drill,used for overhead drilling Churn drill : To make deep holes more than 15cm dia
  6. Shot drill: work on principle of abrasion upto 750mm dia hole can be drilled
  7. Diamond drill:used to obtain core samples
  8. Depth per bit:Depth of hole which can be drilled by bit before replacing Drilling rate:No. of metres of hole drilled per hour per drill
  9. Burden:Horizontal distance from face back to first row of drill hole
  10. Face : Vertical surface extending upward from floor of pit to level@which drilling is done
  11. Piston Drill/Quarry Master:Action similar to wagon drill.It strikes 200 blows per minute Drilling can be done upto 21m
  12. Mast hole drill:Self propelled drill.Used to drill hole on soft to medium rocks.used to drill upto 100m

Selection of Drilling Equipment

  • For exploration purpose – for small cores-Diamond drill & for large cores – Shot drills
  • Blasting – For holes upto 11.25cm in dia use jack hammer or wagon drill.If terrain is rough jack hammer is used.If job is large and terrain permit use of wagon drill prove useful

IMPORTANT CRITERIA

  1. For holes between 12.5cm to 17.5cm in dia choice is Quary Master ,Blast hole drill and churn drill
  2. In soft to medium rock upto 21m deep hole either of above can be used .
  3. For depth greater than 21m deep hole quarry master is not used.
  4. For harder rock blast hole drill not satisfactory .
  5. Then in harder rock more than 21m deep hole churn drill is satisfactory.
  6. For core drilling upto 7.5cm outside hole dia ,Diamond drill is satisfactory.
  7. For 5 to 20cm diamond or shot drill is used.
  8. A diamond drill can drill a hole in any direction while shot drill can drill in vertical direction only 

MOUNTING OF DRILL FOR SMALL TUNNEL

  • For small tunnel ,bar and column are satisfactory but for large tunnel it is convenient to mount drill on jumbos.
  • Inclined hole with inclination 45° prove efficient.If charge of explosive is placed equidistant from two free face it will break 2.25 times more material and if charge of explosive is placed equidistant from three face it will break 3.5 times material than single face quary
  • Igneous rock require more hole than sedimentary rock
  • Maximum efficiency obtain from suitable charge of explosive is when line of resistance is @90° to axis of bore hole and minimum efficiency when two are coincident.
  • Depth of hole: The angle between line of least resistance and axis of bore hole.
  • Depth of hole not more than 5/8 times the diameter of tunnel

 
Drilling Pattern

NOTE:
  1. In Hard rock generally pyramid or wedge cut pattern is employed
  2. The innermost hole called cutholes are 15cm to 23cm deeper than other hole.
  3. Next hole are called Easier’s or reliever hole and are more heavily loaded and outer hole are called rim holes

PATTERN

  1. Horizontal wedge cut:Used when height of tunnel greater than width .When drilling done from bar
  2. Pyramid Cut: For circular or horseshoe tunnel. Apex of cuthole not more then 15cm apart and angle at apex is 50° to 60°
  3. Vertical wedge cut:Best when drilling done from column
  4. Bottom cut : Common in mining and is more efficient . In wide heading modified form of this pattern is used.Modified form called Top cut or Side cut
  5. Buster cut : Also called Baby cut.Used when drilling usually have deep holes. It is drilled about half depth of regular cut holes. Buster cut may be single hole


BASIC DIFFERENCES IN CUT

For Drilling Cut                                                                              For Shaft Cut

1. Horizontal                                                                           1. Central
2. Vertical                                                                                   2. Alternate
3. Pyramid                                                                                   3. Pyramid
 

Comments

Popular posts from this blog

METHOD OF TUNNELING IN SOFT ROCK

A Key article to learn " Method of Tunneling in Soft Rock " providing easy access to learn     Classification of  Method of tunneling in soft rock  1)Hard rock or fully self supporting 2)Soft soils  requiring temporary support during and after construction. Forepoling Method      Sequence of operation The shaft is sunk from surface to the grade level and properly protected with timber sheeting A wooden bent properly braced is setup a few inches from sheeting Small holes at close interval are drilled through the sheeting to facilitate section being cutout.The pattern of holes are 3 inches apart above the cap and other lines of holes below the cap A peice of sheeting is cutout along the top lines of the holes Forepoles or spiles consists of planks with wedge end are entered one at a time and driven through cut,into the ground for half their lengths with an upward inclination of 2 inch per foot. After all the roof and part of sid...

Entrance Locks

Entrance Locks of Harbors and Docks Entrance Locks are those which give access to docks Components of Entrance Locks 1) Chamber: which is enclosed by quays wall on each side and bottom is paved by inverted arch flooring which resists upward water pressure when lock level is low 2) The gates closing entrance constructed of wood or iron of heavy design to withstand water pressure 3) The sill is raised above the gate floor by 2 foot 4) Sluice way   provided in side walls for filling and emptying locks Dimensions of Entrance and Locks It main factor are width, size, and displacement of the longest vessels. Modern locks have width vary from 80 foot and above and depth 25 foot to 40 foot and length of 800 foot and over. Construction of Entrance and Locks Materials   generally used are: 1)Wood 2)Iron Wooden Gates It consists of a horizontal beam that is spaced closer at the bottom to resist water pressure and joined together by heel post in such a way that two extreme ends meet...

Drainage in Tunnel

Load the mind with new topic of tunnel engineering which is  Drainage of Tunnel                         BASICS ABOUT DRAINAGE IN TUNNEL In a tunnel water comes from shafts and portal which is being dug in order to achieve the alignment of tunnel, water which is being used during washing  holes of drill and progressing the tunnel during the time of construction,The water obtained from the first source cannot be easily determined and water obtained from the second cause requires analysis and investigation and can be prevented by RCC bulkhead. Exploding charge may open up a ground water source unexpectedly omitting large quantity of water into the tunnel. Such sudden shot of water give rise to conditions  An underground pocket or lake has been trapped. An underground flow with an inexhaustible source such as river or  lake has been trapped The progress of tunneling work and the maintenance o...